OSC FY 2006 NCAS OCTOBER MONTHLY OPERATIONS
CALENDAR FOR PERIOD 04, ENDING 10/31/2005
(OSC will no longer be providing Client Support on Saturdays)
Note:  Please see the Emergency Special Hours Request procedures if you need to request additional production cycles
ACTIVITY SYSTEM DATE COMMENTS
Inventory Recalculation
IN
10/1/2005
Inventory recalculation first Saturday of every month.
Saturday Hours 
ALL
10/1/2005
Production regions available from 7am to 3pm for online inquiry and keying transactions no production cycle updates.
Close prior period
GL
10/3/2005
September (Period 3) is closed
Escheat Notification
AP
10/3/2005
Escheat checks due to State Treasurer's Office by 11/1/05. Due Diligence letters should have already been mailed. Click on the following link for escheat procedures from the State Treasurer's Office:  http://www.nctreasurer.com/DSTHome/AdminServices/UnclaimedProperty/Default.htm
Health Benefits Interface
FC
10/3/2005
Run monthly Health Benefits Interface.
1099
AP
10/3/2005
Verify Monthly Reports for any necessary corrections.
Balancing to Available Funds Report
BC
10/3/2005
Run the Balancing to Available Funds (BC950) report in XPTR
Pre-Month End Reports
GL
10/3-10/21/05
Pre-month end reports (MOPRE) available in X/PTR.
Payroll Interface
FC
10/5/2005
Run Payroll Interface - Cancellation / Rewrite.
MM Purge
ALL
10/7/2005
Purge scheduled for modules: AP, AR, CC, PS, PC
Saturday Hours
ALL
10/8/2005
Production regions available from 7am to 3pm for online inquiry and keying transactions no production cycle updates.
IT Project Reports
GL
10/10/2005
IT Project Reports in XPTR
Check Reconciliation
AP
10/11/2005
Check Reconciliation tape is posted during production run.
Payroll Interface
FC
10/11/2005
Run Payroll Interface - Mid-Month.
Certified Reports
GL
10/13/2005
Month end reports must be pre-certified by this date.
Saturday Hours 
ALL
10/15/2005
Production regions available from 7am to 3pm for online inquiry and keying transactions no production cycle updates. 
Inventory Recalculation
IN
10/15/2005
Inventory recalculation third Saturday of every month.
IT Project Reports
GL
10/17/2005
IT Project Reports in XPTR
Payroll Interface
FC
10/19/2005
Run Payroll Interface - Cancellation / Rewrite.
Saturday Hours 
ALL
10/22/2005
Production regions available from 9am to 2pm for online inquiry and keying transactions no production cycle updates.
IT Project Reports
GL
10/24/2005
IT Project Reports in XPTR
Current Month End Reports
GL
10/24-10/31/05
Current month end reports (MOCUR) available in XPTR; Pre-month end reports (MOPRE) discontinued
Payroll Interface
FC
10/27/2005
Run Payroll Interface - Monthly.
Saturday Hours
ALL
10/29/2005
Production regions available from 9am to 2pm for online inquiry and keying transactions.
Non-System Checks
AP
10/31/2005
Process Non-System check deletes and cancellations. 
Fixed Assets Monthly Update
FA
10/31/2005
Fixed Asset monthly update process for October, includes depreciation.
Automated closing of PO's
PS
10/31/2005
Automated closing of applicable PO's to receiving and subsequent processing by P&C.
Open next period
GL
10/31/2005
November (Period 05) is opened