ACTIVITY SYSTEM DATE COMMENTS
Close prior period GL 04/02/2001 March 2001 is closed
Pre-Month End Reports GL 04/02/2001 Pre-month end reports available in XPTR working days 1-9.
Health Benefits Interface FC 04/02/2001 Run monthly Health Benefits interface.
Payroll Interface FC 04/04/2001 Run Payroll Interface - Cancellation / Rewrite
Saturday Hours ALL 04/07/2001 Production regions up for processing from 9am to 2 pm
Inventory Recalculation IN 04/07/2001 Inventory recalculation first Saturday of every month
Payroll Interface FC 04/09/2001 Run Payroll Interface - Mid-month
Check Reconciliation CR 04/10/2001 Check Reconciliation tape is posted tonight.
Certified Reports ALL 04/12/2001 Certified reports for March run tonight (9th working day) 
Holiday
ALL
04/13/2001 Production regions down due to Easter Holiday.
Payroll Interface FC 04/18/2001 Run Payroll Interface - Cancellation / Rewrite
Payroll Interface FC 04/26/2001 Run Payroll Interface - Monthly
DAS Checks CR 04/27/2001 Process DAS check deletes and cancels 
Saturday Hours ALL 04/28/2001 Production regions up for processing from 9am to 2 pm
Inventory Recalculation
IN
04/28/2001 Inventory recalculation third Saturday of every month(Special time request 
April Only)
Monthly Update FA 04/30/2001 Fixed Asset monthly update process includes depreciation
Automated closing of PO's MM 04/30/2001 Automated closing of applicable PO's to receiving 